CMTA Terminal Upgrades, Door Replacement and Baggage Claims
Abel’s General Trades Contractor portion of this project includes, but not be limited to, structural modifications required to implement MEP improvements, concrete work, roofing work, landside skylight catwalk framing, site safety (safety barriers, signage and negative air machines), and the non-MEP portions of bathroom, office, baggage handling area, landside terminal, connector and gate renovations. This work shall include, but not be limited to, demo, tiling, ceiling (drop, gypsum and EIFS) installation and finishing, wall construction and finishing, concrete cutting and infill/finishing, and apron-level EIFS work.
1) Phase 1 – Apron Level Bathrooms & “Back of House” Renovations
2) Phase 2 – Landside Terminal Renovation
3) Phase 3 – TSA Checkpoint and Connector Renovation
4) Phase 4 – Airside Terminal Boarding Level Renovation
Project Details
Client:
Louisville Regional Airport